Operation Basis
Regulations on Registration Administration of Customs Declaration Units by the Customs
Scope of Application
1. Complete the infrastructure (±0)
2. Complete construction to top of structure
Required Materials
1. Complete the infrastructure (±0)
(1) Submission of Positive, Negative and Zero Filing of Construction Projects (one paper original and electronic package respectively)
(2) Report on ±0 Testing Results of Construction Projects in Shanghai (one original)
2. Complete construction to top of structure
(1) Submission of Filing of Structure Top (one paper original and electronic package respectively)
(2) Report on Testing Results of Structure Top of Construction Projects in Shanghai (one original)
Application Process
1. The construction unit completes the Submission of Positive, Negative and Zero Filing of Construction Projects or the Submission of Filing of Structure Top and attaches relevant materials
2. Filing by the planning department
Application Location and Contact Information
Room 1713, No. 9 Jilong Road, Pudong New Area, Shanghai
Post Code: 200131
Contact: Liu Linna
Contact Tel.: 021-58698721
Fax: 021-58697739
Complaint Mode
Mode of Complaint to the Management Committee of the China (Shanghai) Pilot Free Trade Zone:
Tel.: 021-58697800
Fax: 021-58698705
E-mail: ftzts@pudong.gov.cn